Roads

 
 

Road Infrastructure In Bankura

The economy of Bankura district is still agrarian in character and the settlement pattern scattered and rural oriented, the network of roads and bridges constitute a critical role with regard to transportation of essential goods and services. The existing road transportation system connects different parts of the district with Calcutta and other important towns.

It is phenomenal that if a region is road way connected with its each settlement then 30 percent development occurs automatically as per the need and culture.

Since this district is a continuation of the Chhotonagpur Plateau, as a result the availability of raw materials is for black top road on one hand and on the other hand the characteristic of soil is favourable for road construction works.

Railway system is also good. The district is mainly served by the South Eastern railway. The existing railway track passing through the district has a connectivity to the important places like Kolkata, Asansol, Kharagpur, Ranchi, Tatanagar, Dhanbad etc.

 

GOVERNMENT OF WEST BENGAL
P.W (ROADS) DIRECTORATE

 

STATUS rEPORT OF ONGOING & PROPOSAL WORKS OF BANKURA HIGHWAY DIVISION, P.W. (ROADS) DIRECTORATE, BANKURA.

 

EXECUTIVE ENGINEER

BANKURA HIGHWAY DIVISION

PUBLIC WORKS (ROADS) DIRECTORATE

March- 2012.

 

1>      INTRODUCTION

1.1>       Bankura Highway Division is one of oldest Division of the P.W. (Roads) Directorate, West Bengal and serving for public providing various mode of work such as construction and maintenance of roads, major and minor bridges, culverts etc. since the year of 1959. So many roads and bridges have been constructed and developed and was now performing as important connectivity within the district.

1.2>       The divisional office located at Nutanchati of Bankura Town beside Saradamani Girls’ College.

1.3>       The total length of road under the jurisdiction of this division is 637.604 Km. Category of roads varies from State Highway to village road. The details are given below:-

State Highway: -             73.90 km.

Major District Road: -     NIL

Other District Road: -  484.304 km.

Village Road: -                  79.400 km.

                                          637.604 km.

Out of this 355.195 Km. is of single lane (2.44 m, 3.05m or 3.80m) width, 282.409 km. is of intermediate lane (5.50m) width.

It is worthy to mention that a length of 132 km. of the above stretches is within Junglemahal (Under Block Sarenga, Ranibandh, Raipur, Simlapal).

1.4>       There are 17(seventeen) number very major bridges over 30 m. Span is located on different roads under this division.

 

2>      ORGANISATIONAL STRUCTURE OF THE DIVISIONAL OFFICE:-

The Bankura Highway Division is a vertical arm of State Highway Circle-VI, Paschim Midnapore. There are four Sub divisions under the division, namely, Bankura West Highway Subdivision at Bankura, Bankura East Highway Subdivision at Bankura, Bishnupur Highway Subdivision at Bishnupur, Kangsabati Bridge Highway Subdivision at Khatra.

   

REPORT OF PROJECTS IMPLEMENTED FROM MAY 2011 TILL DATE IN LWE AREAS

 

Name of Department : Bankura Highway Division ,P.W.(Roads) Directorate.

 

 

 

 

Name of Sector

Name of scheme

Name of block where the scheme is implemented

Sanctioned amount (Rs. In lakh)

Fund utilized

(Rs. In lakh)

Physical progress

Remarks

 

 

 

 

 

 

 

 

 

 

No Project is implemented since May’2011

  

 Following work under 13th Finance Commission for the Financial Year 2011-2012

In LWE Areas.

REPORT OF PROJECTS IMPLEMENTED FROM MAY 2011 TILL DATE IN LWE AREAS

 

Name of Department: Bankura Highway Division, P.W. (Roads) Directorate.

 

 

 

 

Name of Sector

Name of scheme

Name of block where the scheme is implemented

Sanctioned amount (Rs. In lakh)

Fund utilized

(Rs. In lakh)

Physical progress

Remarks

 

Road

Surfacing work of Ranibandh-Jhilimili Road from 11.00 kmp to 20.00 kmp

Raipur

70.20

Nil

10%

Work in progress, Likely to be completed by March’2012

 

Road

Surfacing work of Krishnapur-Raipur-Phulkusma-Benagoria Road from       1.00 kmp to 4.00 kmp

Sarenga

33.00

Nil

85%

Work in progress, Likely to be Completed by31.03.2012

 

Road

Surfacing work of Krishnapur-Raipur-Phulkusma-Benagoria Road from     14.00 kmp to 17.00 kmp

Raipur

33.00

Nil

100%

Work completed

 

Road

Surfacing work of Krishnapur-Raipur-Phulkusma-Benagoria Road from     18.00 kmp to 21.00 kmp

Raipur

33.00

Nil

100%

Work completed

 

Road

Surfacing work of Krishnapur-Raipur-Phulkusma-Benagoria Road from    22.00 kmp to 27.20 kmp

Raipur

57.20

Nil

70%

Work in progress, likely to be completed by 31/03/2012

 

  

Following work under 13th Finance Commission for the financial year 2011-2012

In LWE Areas

REPORT OF PROJECTS IMPLEMENTED FROM MAY 2011 TILL DATE IN LWE AREAS

 

Name of Department: Bankura Highway Division, P.W. (Roads) Directorate.

 

 

 

 

Name of Sector

Name of scheme

Name of block where the scheme is implemented

Sanctioned amount (Rs. In lakh)

Fund utilized

(Rs. In lakh)

Physical progress

Remarks

 

Road

Surfacing work of Bishnupur-Patrasayer Road from 18.00 kmp to 20.00 kmp

Simlapal

19.00

Nil

100%

Work completed

 

Road

Surfacing work of Simlapal-Krishnapur Road from 2.00 kmp to 4.00 kmp

Simlapal

21.00

Nil

100%

Work completed

 

Road

Surfacing work of Simlapal-Krishnapur Road from 4.00 kmp to 6.00 kmp

Simlapal

21.00

Nil

100%

Work completed

 

Road

Surfacing work of Simlapal-Krishnapur Road from 6.00 kmp to 7.50 kmp

Simlapal

15.75

Nil

100%

Work completed

 

Road

Surfacing work of Simlapal-Krishnapur Road from 7.50.00 kmp to 9.00 kmp

Sarenga

15.75

nil

100%

Work Completed

 

 Proposal of projects in LWE Areas

REPORT OF PROJECTS IMPLEMENTED FROM MAY 2011 TILL DATE IN LWE AREAS

 

Name of Department: Bankura Highway Division, P.W. (Roads) Directorate.

 

 

 

Name of Sector

Name of scheme

Name of block where the scheme is implemented

Not yet Sanctioned Amount (Rs. In lakh)

Fund utilized (Rs. In lakh)

Physical progress

Remarks

Road

Widening &Strengthening of Krishnapur-Raipur-Phulkusma-Benagoria Road from    0.00 kmp to 27.20 kmp (SH)

Raipur

Rs.  2631.47

 

 

Submitted under Backward Region’s Grant Fund

Road

Widening & Strengthening of Ranibandh-Jhilimili Road from        0.00 kmp to 21.00 kmp(ODR)

Ranibandh

Rs. 1333.34

 

 

Submitted under Backward Region’s Grant Fund

Bridge

Construction of bridge over Bhairabbanki at 21st km of Krishnapur-Raipur-Phulkusma-Benagoria Road

Raipur

Rs.   800.00 (Rough cost estimate)

 

 

DPR being prepared by Highway Design Division-I

Road

W&S of Chandrakona-Goaltore-Sarenga-Simlighat Road from 29 to 31.80 kmp. Width : 3.80m

Sarenga

Rs. 351.16 (not sanctioned)

 

 

Estt. submitted, File No.-3P-23/10

Road

W&S of Simlapal-Sarenga-Bamundiaghat Road from 17 to 21.40 kmp  Width : 3.05m

Sarenga

Rs. 389.31 (not sanctioned)

 

 

Estt. submitted, File No.-4P-4/06

 

WORK DETAILS OF ROADS UNDER P.W.(ROADS) DIRECTORATE

Name of Division :- Bankura Highway Division,       (Ongoing Work)

Sl. No.

Name of Projects

Stretch

Project length

(km)

Sanction Amount

(Rs. In Lakh)

Head

Physical progress

Remarks

Roads (Ongoing works)

1

Imp. Of Indus-Sashpur-Akui Rd from 0.00 to 7.00km. (Total length= 14.00km)

0-7 kmp

7 km

607.43

Plan

100%

Completed

2

Improvement & widening of Chatna-Dalpur-Bishpuria road from 0.00 kmp. To 17.45 kmp. (Sanctioned No IM-35/08/370-R/PL dt. 27.05.2008).

0-17.45 kmp

17.45 km

491.74

RIDF-XIV

100%

Work completed

3

Construction of balance work of link road to bridge at Samroghat (Sanctioned No IM-35/08/370-R/PL dt. 27.05.2008).

6.409-9.089 & 9.860-10.65kmp

3.47km

389.33

RIDF-XV

100%

Completed

4

Surfacing work of Ranibandh-Jhilimili Road from 11.00 kmp to 20.00 kmp

11-20 kmp

9 km

70.20

13th F.C.

10%

Work in progress

5

Surfacing work of Bishnupur-ByePass Road from 0.00 kmp to 5.20 kmp

0-5.20 kmp

5.20 km

55.00

13th F.C.

100%

Work completed

6

Surfacing work of Bishnupur-Patrasayer Road from 20.00 kmp to 26.00 kmp

20-26 kmp

6 km

57.00

13th F.C.

100%

-Do-

7

Surfacing work of Krishnapur-Raipur-Phulkusma-Benagoria Road from       1.00 kmp to 4.00 kmp

1-4 kmp

3 km

33.00

13th F.C.

100%

-Do-

8

Surfacing work of Krishnapur-Raipur-Phulkusma-Benagoria Road from     14.00 kmp to 17.00 kmp

14-17 kmp

3 km

33.00

13th F.C.

100%

-Do-

9

Surfacing work of Krishnapur-Raipur-Phulkusma-Benagoria Road from     18.00 kmp to 21.00 kmp

18-21 kmp

3 km

33.00

13th F.C.

100%

-Do-

10

Link Road to Ramchandrapur Health Centre from 0.00 kmp to 7.00 kmp

0-7 kmp

7 km

183.08

Plan

15%

Work in progress

11

Surfacing work of Krishnapur-Raipur-Phulkusma-Benagoria Road from    22.00 kmp to 27.20 kmp

22-27.20 kmp

5.20 km

57.20

13th F.C.

70%

Work in progress

12

Surfacing work of Bishnupur-Patrasayer Road from 16.00 kmp to 18.00 kmp

16-18 kmp

2 km

19.00

13th F.C.

100%

Work completed

13

Surfacing work of Bishnupur-Patrasayer Road from 18.00 kmp to 20.00 kmp

18-20 kmp

2 km

19.00

13th F.C.

100%

-Do-

14

Surfacing work of Simlapal-Krishnapur Road from 2.00 kmp to 4.00 kmp

2-4 kmp

2 km

21.00

13th F.C.

100%

-Do-

15

Surfacing work of Simlapal-Krishnapur Road from 4.00 kmp to 6.00 kmp

4-6 kmp

2 km

21.00

13th F.C.

100%

-Do-

16

Surfacing work of Simlapal-Krishnapur Road from 6.00 kmp to 7.50 kmp

6-7.50 kmp

1.50 km

15.75

13th F.C.

100%

-Do-

17

Surfacing work of Simlapal-Krishnapur Road from 7.50.00 kmp to 9.00 kmp

7.50-9 kmp

1.50 km

15.75

13th F.C.

100%

-Do-

Inspection Bunglow

1

Bishnupur Inspection Bunglow

Bishnupur

 

59.49

Plan

 

Architectural plan under preparation by Chief Govt. Architect, Govt.o f West Bengal

   

Bridges (Ongoing Work)

1 Replacement of damaged arch Bridge at 17.50 km of Bishnupur –Sonamukhi-Rangamati Rd.(4m x 4m x 5 cell) At 17.5km 22.60 km 91.04 Plan 88% Work is in progress
2

Constn. of balance work of RCC Bridge over river Darakeswar at Samroghat Bridge at 10km of Kotulpur-Indus Road

Sanctioned No (NB (WBRO)/761/SPD 20 9XV-103rd. PSC/ 2009-10 dt 06.05.09)

At 10th km

371 m
 


837.71

RIDF-XV

24% Work is in progress
3

Constn. Of Box Bridge on Taldangra-Panchmura-Chowbeta Road.


At 9th Km.


At 34th. km

At 9th

   &

34th km

34.00 m


22.40 m

170.84
RIDF-XV
100% Work Completed
4 Balance portion of proposed bridge over river Kangsabati at Kechandaghat on Bankura-Ranibandh Road in the District of Bankura.

At 52nd km

275m Previous sanction Amount Rs.735.43 Plan

Work of foundation completed-90% Revised estimate(Rs. 820.72) submitted for revised  administrative approval

  

WORK DETAILS OF ROADS UNDER P.W.(ROADS) DIRECTORATE

Name of Division :- Bankura Highway Division,      (Proposal Work)

Sl. No.

Name of Projects

Stretch

Project length

(km)

Sanction

/Estimated Amount

(Rs. In Lakh)

Head

Physical progress

Remarks

Bridges (Proposal Works)

1

Replacement of old arch bridge by Box culvert at 27th km of Taldangra-Panchmura-Chowbeta Road(Saldah Khal)

At 27th km

 

84.44

Plan

 

Fresh proposal and D.P.R under preparation by Bridge Planning Circle, P.W(Roads)D

2

Construction of bridge over  river Sali at 30th km of Bishnupur-Sonamukhi-Rangamti Road

At 30th km

 

1074.00

Plan

 

Estt. Submitted. File under process.

3

Construction of bridge over Khal  at Samrughat at 11thh km of Kotulpur-Indus- Road

At 11th km

 

326.69

Plan

Technical sanction is awaited

Estt. Submitted. Sanctioned under plan head. Technical sanction is awaited.

4

Construction of bridge over Bhairab Banki at 21st km of Krishnapur-Raipur-Phulkusma-Benagoria Road

At 21st km

 

800.00

(Rough cost)

Plan

 

DPR being prepared by Bridge Planning Circle, P.W (Roads) Dte

5

Replacement of damaged arch bridge at 19th km of Bishnupur-Sonamukhi- Rangamati Road

At 19th km

 

100.00

Plan

 

Estt. Submitted. Not sanctioned

Roads(Proposal Works)

1

Widening & Strengthening of Krishnapur-Raipur-Phulkusma-Benagoria Road from    0.00 kmp to 27.20 kmp (SH)

0-27.20 kmp

27.20 km

2631.47

Backward Region’s Grant Fund

 

Estt. Submitted . Technical sanction awaited for tender processing.

2

Widening & Strengthening of Ranibandh-Jhilimili Road from        0.00 kmp to 21.00 kmp(ODR)

0-21 kmp

21 km

1333.34

Backward Region’s Grant Fund

 

Estt. Submitted . Technical sanction awaited for tender processing.

3

Strengthening of Indpur-Belut Road from 0.00 kmp to 20.40 kmp (VR)

0-20.40 kmp

20.40 km

1223.13

Backward Region’s Grant Fund

 

Estt. Submitted . Technical sanction awaited for tender processing.

4

Widening & Strengthening of Bishnupur Bye Pass Road from        0.00 kmp to 5.20 kmp (SH)

0-5.20 kmp

5.20 km

706.02

Backward Region’s Grant Fund

 

Estt. Submitted . Technical sanction awaited for tender processing.

5

Strengthening of Bishnupur-Sonamukhi-Rangamati Road from   0.00 kmp to 6.00 kmp (ODR)

0-6 kmp

6 km

521.94

Backward Region’s Grant Fund

 

Estt. Submitted . Technical sanction awaited for tender processing.

6

Widening & Strengthening of Gangajalghati-Saltora Road from     0.00 kmp to 22.00 kmp (ODR)

0-22 kmp

22 km

1780.51

Backward Region’s Grant Fund

 

Estt. Submitted . Technical sanction awaited for tender processing.

7

W&S of Chandrakona-Goaltore-Sarenga-Simlighat Road from 29 to 31.80 kmp. Width : 3.80m

29-31.80 kmp

2.80 km

351.16

Plan

 

Estt. Submitted. File No.-3P-23/10

Not sanctioned

8

W&S of Simlapal-Sarenga-Bamundiaghat Road from 17 to 21.40 kmp  Width : 3.05m

17-21.40 kmp

2.40 km

389.31

Plan

 

Estt. Submitted.File No.-4P-4/06.

Not sanctioned

9

W&S of Gangajalghati-Enayetpur road from 0.00 to 16.00kmp. Width : 3.05m

0-16 kmp

16 km

754.25

Plan

 

Estimate submitted. File No 3P-138/10

Not sanctioned

10

Improvement of Sashpur-Dighalgram road from 1.50 to 6.50 kmp. Width : 2.44m

1.5-6.5 kmp

5 km

468.27

Plan

 

Estimate submitted

File No.-3P-22/10

Not sanctioned

11

Improvement of Chhatna Bye-Pass Road from 0.00 to 1.90kmp Width : 5.50m

0-1.9 kmp

1.9 km

53.00

Plan

 

Estt. Submitted. File No.-3P-122/10

Not sanctioned

12

Widening & Strengthening of Indus Sashpur Akui Road (L-14 Km)

7-14 kmp

7.00 km

879.00

RIDF-XVII

 

Estt. Submitted. Likely to be sanctioned

13

Behar-Bamunia Road (2nd Phase) 5.00 kmp to 15.00 kmp

5-15 kmp

10 km

1401.53

Plan

 

Estt. Submitted. Not sanctioned

14

Widening and strengthening of Simlapal-Sarenga-Bamundihaghat Road from 21.4Km to26.20Km

21.40Km -26.20Km

3.80Km

236.42

Plan

Under tender process

Administrative approval granted.